Installation ManualSite Preparation

Site Preparation

Factory Floor Requirements

Proper site preparation ensures safe installation, adequate access for maintenance, and stable machine operation.

Space Requirements

DimensionRequirement
Machine footprintSee machine data sheet for specific model
Front clearance (operator side)≥ 2.5 m
Rear clearance (safety door side)≥ 1.5 m
Left / right clearance≥ 1.0 m each side
Above machine≥ 1.0 m clearance for crane / hoist access
Controller cabinet clearance≥ 0.8 m in front of cabinet for door swing

Floor Requirements

ParameterStandard
Floor typeReinforced concrete
Minimum thickness200 mm (for machines ≤ 2000 kN), 300 mm (for > 2000 kN)
Concrete grade≥ C25 (25 MPa compressive strength)
Surface flatness≤ 3 mm over 2 m length
Floor slope≤ 1:1000
Floor loading capacity≥ 2× machine weight (with mold, material, and auxiliaries)
⚠️

Always verify floor load capacity with a structural engineer before installation. Insufficient floor strength can cause foundation settlement, machine misalignment, and safety hazards.

Environmental Conditions

ParameterRequirement
Ambient temperature5–40°C
Humidity30–85% RH (non-condensing)
Lighting≥ 300 lux at operating panel, ≥ 150 lux in machine area
VentilationAdequate for heat dissipation (consult machine heat rejection data)
Air qualityNo corrosive gas, no conductive dust
VibrationFloor vibration < 0.5 mm/s (from nearby presses or equipment)

Foundation Preparation

For machines larger than 5000 kN or where the floor loading is marginal, a dedicated foundation pit is recommended.

Machine TonnageFoundation Pit DepthRebar Specification
≤ 2000 kNNot required (level on floor)
2000–5000 kN300–500 mmØ12 mm @ 200 mm grid
> 5000 kN500–800 mmØ16 mm @ 150 mm grid

Utilities Checklist

UtilityPreparation
Main powerRun cable from main distribution panel. Install dedicated circuit breaker per machine.
GroundingInstall grounding rod (resistance ≤ 4Ω). Run ground cable to machine location.
Cooling waterRun supply and return pipes with shut-off valves. Install pressure gauge and flow meter.
Compressed air (if required)Run air line with pressure regulator, filter, and shut-off valve.
DrainageProvide floor drain or collection pit for hydraulic oil containment.
Network / IoTRun Ethernet cable for Hwamda Connect IoT module (optional).

It is strongly recommended to install a dedicated transformer and power distribution panel for injection molding machines to isolate them from other factory loads and reduce electrical noise.