Maintenance ManualYearly / 2000h Maintenance

Yearly / 2000h Maintenance

Perform yearly maintenance after every 2000 hours of operation (or annually, whichever comes first). Estimated time: 4–8 hours. Some tasks may require specialized tools or external service providers.

Hydraulic System

TaskDetails
Complete hydraulic oil changeAlways perform yearly regardless of oil analysis results. Use OEM-approved grade and quantity.
All filter elements replacementReplace suction, return, high-pressure, and off-line filter elements.
Tank cleaningOpen tank manhole, clean all internal surfaces, magnetic rods, and baffles.
Hydraulic pump overhaul (if indicated)Replace shaft seal, bearings, and wear plate if pump running hours exceed OEM recommended interval (typically 15000–20000h).
Valve overhaulInspect servo-proportional valves. Replace pilot filters, O-rings. Perform null bias calibration.
Cylinder seal replacementReplace all cylinder rod seals and wiper rings preventatively.
Hose replacementReplace all flexible hydraulic hoses (max service life 5–6 years per ISO 8331).
Accumulator overhaulReplace bladder/diaphragm, check shell integrity.

Electrical System

TaskDetails
Controller backup batteryReplace lithium battery on controller CPU module and servo drives.
Main contactor replacementPreventative replacement of main power contactors.
Servo drive capacitor checkMeasure DC bus capacitance or replace per OEM schedule (typically 5–7 years).
Full megger testTest all motor windings, heater circuits, and DC bus to ground.
Cable replacementReplace high-flex cables in drag chains showing wear.
Cleaning / overhaul of main breakerCheck main breaker mechanism, torque all terminals.

Mechanical System

TaskDetails
Tie bar inspection for cracksPerform magnetic particle (MT) or ultrasonic (UT) inspection on all four tie bars.
Screw and barrel inspectionRemove screw, inspect flight wear pattern, measure barrel I.D. Replace if worn beyond tolerance.
Non-return valve (check ring)Inspect check ring and seat for wear. Replace if gap > 0.1 mm.
Clamp toggle bushing replacementReplace all toggle joint brass bushings.
Platen surface inspectionCheck platen surface flatness. Re-surface if damaged.
Guide rail replacement (if worn)Measure guide rail clearance. Replace gibs or guide shoes.

Safety System

TaskDetails
Safety relay testTest all safety relay modules per manufacturer procedure.
Door switch replacementReplace safety door switches (preventative, regardless of condition).
E-stop button checkVerify all E-stop buttons function and have correct labels.
Light curtain test (if equipped)Perform full light curtain function test.
Hydraulic safety valve testTest hydraulic dump valve / safety block functionality.
Ground bonding verificationVerify all panels, doors, and machine frame bonded to ground.

Yearly maintenance is the ideal time to perform machine upgrades — such as retrofitting IoT sensors, upgrading the controller software, or replacing older servo drives with current-generation models.