Installation ManualInitial Startup & Functional Check

Initial Startup & Functional Check

Pre-Power Checks

Before applying power for the first time:

SystemCheck
ElectricalMain breaker OFF. All sub-breakers OFF. E-stop pressed. Control transformer primary voltage matches supply.
GroundingGround connection verified (≤ 4Ω). All panels bonded.
Cooling waterWater supply ON, flow verified, no leaks.
HydraulicOil level at 3/4 of sight glass. All ball valves OPEN. Tank breather installed.
MechanicalNo shipping braces remaining. All guards installed. Tie bar nuts at correct position. Injection unit at full retract.
SafetyAll E-stop buttons wired and functional. Safety door switches connected.
MoldIf mold installed: verify it fits within tie bar space, weight within platen capacity, center height matches nozzle.

First Power-On Sequence

Close main breaker

Energize the machine. The controller will start up (60–90 seconds). Observe the HMI for startup diagnostics.

Check control voltage

Measure 24 VDC supply at the controller power input. It must be 23.5–25.0 VDC.

Close servo breaker

Energize the servo drive. Observe the drive display for normal status (typically “rdy” or “RUN”). No fault codes should appear.

Reset E-stop

Release all E-stop buttons and close all safety doors. The safety circuit should reset.

Close heater breaker

Energize heater circuits. Start barrel heating. Set temperature to 140–160°C for drying (if material is loaded) or to 50°C for warm-up only.

Start hydraulic pump (hydraulic machines only)

Press the pump start button. Listen for abnormal noise. Monitor oil pressure:

  • Low-pressure idle: 5–15 bar
  • After warm-up, high-pressure standby: system pressure (typically 140–175 bar)
⚠️

On first startup, if the hydraulic pump motor phase sequence is reversed, the pump will rotate backward. This can damage the pump within seconds. Verify phase sequence BEFORE starting the pump or listen for abnormal sound and stop immediately if the pump does not build pressure.

Functional Testing

Clamp Unit

TestProcedureAcceptance
Open/close at low speedSet speed to 20%, full stroke open and closeSmooth motion, no binding or unusual noise
Clamp force buildIncrease to 50% rated forcePressure holds steady, all tie bars load evenly
Mold safety / low-pressure protectionWith mold 500 mm open, close at low speedSystem detects no resistance (with no mold on small machines, may need to adjust threshold)

Injection Unit

TestProcedureAcceptance
Carriage forward/retractFull stroke at low speedSmooth, no hesitation
Injection (no material)Screw forward at 10% speed for max 3 secondsSmooth motion
Screw rotation (no material)Rotate at 20 RPM for 5 secondsSmooth rotation, no grinding

Ejector Unit

TestProcedureAcceptance
Ejector advance/retreatFull stroke forward and back, repeat 5 timesSmooth motion, correct position feedback
Ejector stroke settingAdjust stroke to 80% and cycleStops at correct position

Temperature Control

TestProcedureAcceptance
All zones heatingSet all zones to 180°CAll zones reach setpoint within 30 minutes
Thermocouple checkCompare HMI reading with independent thermocoupleAll zones within ±5°C
SSR operationCheck each zone current drawEach zone draws expected current

Safety System

TestProcedureAcceptance
Emergency stop (each button)Press E-stop during clamp closeImmediate stop, servo de-energize, pump stop
Safety door (front)Open during automatic cycleCycle stops immediately
Safety door (rear)Open during automatic cycleCycle stops immediately
Low-pressure mold protectionPlace a 3 mm thick soft material (cardboard) on mold face, close moldMold stops and reverses
Light curtain (if equipped)Break light curtain during clamp closeImmediate stop

First Cycle

  1. Set temperature to process parameters for the material being used.
  2. Allow 20–30 minutes soak time after reaching setpoint.
  3. Load material into the hopper.
  4. Purge 5–10 shots of material to stabilize temperature.
  5. Set injection parameters to conservative values (mid-range speed and pressure).
  6. Execute one complete semi-automatic cycle.
  7. Inspect the part — check for short shots, flash, sticking, or other defects.
  8. Adjust parameters gradually (one change at a time) until the part is acceptable.
  9. Run 20 continuous cycles and check shot weight repeatability.

During the first 100 cycles, pay close attention to oil temperature, vibration, and unusual sounds. This is the machine’s “break-in” period. Small adjustments to leveling, lubrication, or parameters are normal.